Thursday, October 16, 2025

Oahu rail

10/16/25 - Segment 2 opens to public
9/27/25 - Hanabusa resigns from HART board
12/29/24 - HART to request eminent domain for seven properties
8/16/24 - HART awards $1.66B contract for Skyline’s final segment
9/17/23 - HART projects $580 million surplus at completion (next decade)
6/29/23 - Some HART board members say Kahikina could pay greater deference
6/29/23 - The rail doesn't quite stop at Pearlridge
6/25/23 - Rail is finally ready to roll (the first part anyway)
6/17/23 - Rail system is named "Skyline"
6/2/24 - Kahikina's future as CEO in doubt
5/11/23 - First phase to launch on June 30
2/22/23 - Construction on Dillingham scheduled to last through 2026
10/1/22 - FTA approves shorted rail route
9/4/22 - Shortened rail route will mean more traffic in Kakaako
8/30/22 - Rail system moving into trial runs
8/5/22 - Cracks in concrete could delay rail opening
7/12/22 - Former consultant reassigned after raising design issues
6/5/22 - HART submits rail recovery plan to FTA 
3/20/22 - Shorter route could save over $200 million in legal fees
3/16/22 - Blangiardi cuts rail route short
12/5/21 - David Shapiro: HART's continuing free ride
11/21/21 - Rail numbers have been shifty (David Shapiro)
11/18/21 - Rail deficit estimate cut to "only" $2 billion
10/10/21 - Heavyweights in favor of raising hotel room taxes to pay for rail
10/10/21 - David Shapiro: rail leaders need to show that they know what they're doing
6/28/21 - Rail project continues to face uncertainty
5/13/21 - What now?  Replace the wheels?
5/11/21 - Hanabusa declines $924,000 and will serve on HART's board without compensation
4/2/21 - Lori Kahikina Q&A
3/11/21 - Rail project has a $3 billion shortfall with no answers
1/3/21 - All David Shapiro is saying is give Kahikina a chance
12/28/20 - Lori Kahikina named interim chief of rail project
12/24/20 - Robbins leaves with rail line from Kapolei to Halawa scheduled to open in 2021
12/17/20 - Robbins not expected to be renewed
11/20/20 - Robbins finally moving on from P3

11/18/20 - Looking back at the 8/31/2008 Advertiser, the project was due to break ground in December 2009 at a cost of $3.7 billion
11/18/20 - Caldwell says cost of rail up to $11 billion and won't be complete until 2033

11/13/20 - Nevertheless Robbins persists in submitting P3 report
11/1/20 - All Andrew Robbins is saying, is give P3 a chance
10/25/20 - Kirk Caldwell: pulling out of PPP and steps to get back on track
10/25/20 - Editorial: HART must recalibrate
10/25/20 - David Shapiro: a mad rush is imprudent
10/22/20 - HART discussing building rail in phases
10/15/20 - Dennis Callan says they are still real solutions possible

[10/9/20] Caldwell wants to put the heat on Robbins
[10/8/20] How about ending rail at Chinatown?

[5/13/20] First segment opening pushed back to March 2021

[3/4/20] Two new bus routes planned to augment rail system

[2/27/20] Rail contractor snags lines closing Dillingham Blvd.

[12/29/19] Hawaiian names possibilities for train stations [David Shapiro]

[9/9/19] Yamanoha well-suited for HART

[7/14/19] Heidi Tsuneyoshi seeking more information from HART

[5/8/19] FTA insisting city commit $25 million this year before releasing more funds

[4/19/19] City now plans to open segments of rail in 2020 and 2023

[4/14/19] Hart committed to finishing rail to Ala Moana

[4/4/19]  Middle Street better than Ala Moana for transfers [Dennis Callan]

[4/1/19] Stopping rail at Middle Street might save only $450 million

[3/31/19] Lee Cataluna: debacle is right

[1/19/19] HART responds that many of the issues raised by the audit have been addressed and most of the recommendations of the audit have been or are being implemented

[1/18/19] City auditor finds HART violated procurement requirements

[11/7/18] Architects say to change rail route to U.H.-Manoa because of future flooding

[11/2/18] Caldwell signs bill to allow City to help pay for rail

[10/21/18] State audit of rail transit not going smoothly

[3/11/18] Slater and Roth call for rail to end at Middle Street

[10/3/17] Caught this discussion on Olelo on Option 2A which is an alternative street level rail system from Middle Street.  The panel seemed pretty intelligent and experienced.  (but see 2/5/17 and 2/8/17 below)
[9/19/17]  Mufi on Andrew Robbins (page 22)

[9/6/17] City Council votes to extend excise tax surcharge to 2030
[9/6/17] Ige signs into law the $2.4 billion bailout package
[9/2/17] House votes 31-15 in favor of rail deal
[8/30/17] State Senate votes 16-9 in favor for rail bailout bill
[8/29/17] Rail bill passes out of committee 5-4

[8/25/17] House and Senate announce $2.37 billion rail bailout package / yelling ensues, Caldwell walks out of meeting

[8/1/17] Andrew Robbins gets a second chance

[7/13/17] City Council authorizes $350 million of bonds to get rail to Middle Street

[6/20/17] Randall Roth says it's time to cut our losses

[6/20/17] Lawmakers haven’t yet agreed on the details, but leaders in the state House and Senate announced Monday that they plan to hold a special session this summer to try to resolve their impasse over how to provide more funding for the city’s 20-mile rail project.

[6/8/17] Motor vehicle weight taxes, bus fares and parking rates will go up under a 2018 budget package approved by the Honolulu City Council on Wednesday.

The budget package was highlighted by skirmishes over what fees and rates would go up and which would not. The Caldwell administration said “revenue enhancements” were necessary — without raising property tax rates — largely to deal with rising fixed costs and collective bargaining increases, as well the anticipated costs of operation and maintenance of the rail line.

[6/8/17] The Council’s 6-3 decision on Wednesday, which hinged on Councilman Trevor Ozawa’s swing vote, authorizes up to $350 million in city general obligation bonds for rail. Those funds will help cover the contracts to build the system as far as Middle Street, and future general excise tax surcharge dollars are expected to eventually repay the bonds.

Without that authorization Wednesday, work on the transit system’s elevated concrete pathway and its stations would have stalled at Aloha Stadium in early 2018, and the rail agency overseeing construction, unable to pay its bills, would have started shedding staff and trimming its operations to a bare minimum this August, project officials said.

[5/5/17] A divided state Legislature closed out the turbulent 2017 session and headed home Thursday without approving any bill to provide more funding for rail, but Honolulu Mayor Kirk Caldwell said he plans to press lawmakers for a new rail funding agreement that could be ratified in a special session later this year.

In a rare closing-day leadership shake-up, House Speaker Joseph Souki resigned from his post at the request of his colleagues Thursday morning, and House lawmakers voted to elevate House Majority Leader Scott Saiki to the speaker’s job in a final floor session that Souki did not attend.

In the Senate, Ways and Means Committee Chairwoman Jill Tokuda made a tearful speech praising her staff and putting her colleagues on notice that she has further political plans.

Tokuda’s colleagues have agreed to remove her from the powerful Ways and Means post, which controls all tax and appropriations measures in the Senate. Tokuda has described that as a “power grab” related to the sometimes bitter rail debate.

Souki thanked the people of Hawaii and the members of the House in his resignation letter, “especially those who have stood with me through thick and thin.”

He said he regretted that lawmakers were unable to “do the work of the people” by reaching agreement this year on bills to provide billions of dollars in new funding for the Honolulu rail project, and on a bill to allow physicians to prescribe lethal medications to people with terminal illnesses.

The decision to remove Souki didn’t sit well with some lawmakers, including Rep. Marcus Oshiro and Rep. Sharon Har, who called the removal of Souki “unprecedented.”

[5/4/17] Tokuda and Souki to be ousted due to rail

[4/21/17] Cayetano ad urges Trump to withhold funding for Honolulu rail

[2/8/17] At-grade light rail won't work says Krishniah Murray

[2/5/17] Salvage the Rail report touts at-grade rail

[12/25/16 Randall Roth] Rail was supposed to cost $3 billion … then $4.6 billion … then $5.2 billion. The latest official estimate is $8.1 billion … but the city reportedly is thinking about raising it to $9.5 billion.

The city claims that the percentage of commuters who use public transportation will increase from 6 percent to 7.4 percent once rail has been built. But most cities have experienced a decline in bus ridership as money is diverted from the existing bus system to pay for rail operations and maintenance. The combined rate for bus and rail is usually less than was the rate for just the bus.

It’s not too late to convert the existing guideway to use by bus rapid transit. Some of the saved money could then be used to reduce traffic congestion, such as by installing flyovers and bypasses in chokepoint areas like the Middle Street merge; adding new contraflow and bus-on-shoulder options; adding new traffic lanes to existing roads; and expanding Honolulu’s bus system, such as by increasing the number of express buses that go where commuters want to go, rather than eliminating most of them, as is part of the current rail plan.

[12/3/16] Rail price tag could rise to $9.5 billion

[10/28/16] Nohara to replace Hanabusa on rail board
[10/28/16] Interim CEO hired for one year

[10/17/16] Caldwell and Charles Djou disagree over how to pay for rail.

[9/30/16]  Local rail leaders have raised their estimate yet again for how much it will cost to complete the cash-strapped 20-mile transit project, now putting the price tag at more than $8.6 billion.

They’ve also added another year of delay to rail’s schedule, mostly thanks to the ongoing dilemma about how to fund the elevated project’s final leg into town. Rail leaders now estimate that train cars will start running across the full line from East Kapolei to Ala Moana Center starting in December 2025.

Originally, under the city’s deal with federal transit officials, the rail was supposed to cost $5.26 billion. The full line was to start running in January 2020.

[9/29/16] Years before any trains will carry commuters across the island, cracks are forming in the plastic padding used to give the train tracks a level surface, and strands in three of the tendons that help keep the guideway structure in place have snapped apart, according to reports issued by the Honolulu Authority for Rapid Transportation and the rail project’s federal oversight agency.

[9/1/16]  Both remaining candidates for Honolulu mayor are now on the same page, saying the city must build an elevated rail line all the way to Ala Moana Center.

Former U.S. Rep. Charles Djou, who is challenging Mayor Kirk Caldwell’s re-election bid, said Wednesday that the message federal transit officials gave to the city this week requires him to back off his position to seek alternatives to heavy rail to get from Middle Street to Ala Moana.

“We have to do rail, we have to take it to Ala Moana,” Djou said. “It has to be elevated, and it has to be heavy rail, period.”

Caldwell and Council Chairman Ernie Martin said Tuesday that Federal Transit Administration leaders are firm that the rail line needs to be constructed to Ala Moana or the city may be in breach of an agreement that gave the city up to $1.55 billion in federal dollars. Also, city leaders were unsuccessful in their attempts to get the FTA to provide more funding to make up a shortfall of up to $2 billion.

Djou’s message through the first three months of the campaign had been that rather than commit to building elevated rail to Ala Moana as supported by Caldwell and former Mayor Peter Carlisle, the city should explore every option from a bus rapid transit system to putting the line at ground level through Kalihi.

But on Wednesday, Djou said he is now willing to consider asking the state Legislature for an extension of Oahu’s 0.5 percent surcharge on the general excise tax — but only if, as mayor, he determines the city has no other alternative.

[8/31/16] City leaders are expected to return to the Legislature this winter to seek an extension of the 0.5 percent general excise tax surcharge for the $8 billion rail project because their efforts to secure additional federal dollars were shot down by top federal transit officials in San Francisco this week.

The request, however, is likely to be met with skepticism by state lawmakers frustrated that they once again are being asked to take the political hit for a project that has climbed in price by more than $2 billion since they agreed two sessions ago to a five-year extension of the surcharge through 2027.

The Federal Transit Administration also made it clear during two days of meetings that halting rail construction at Middle Street — rather than in the Ala Moana area [at least to Aloha Tower], as the city originally planned — is not acceptable, and the agency warned that stopping the line short could jeopardize $1.55 billion in federal grants, city officials said.

City and federal transit officials announced in the spring that building rail now likely will cost a projected $8 billion for the full 20 miles, from East Kapolei to Ala Moana Center, with 21 rail stations. That’s about $2 billion more than the cost estimate made two years ago. Consequently, they said, there would be only enough money to reach the Middle Street station, about 5 miles short of Ala Moana.

Both Mayor Kirk Caldwell and City Council Chairman Ernie Martin said Tuesday they asked FTA officials for additional funding and were told none would be made available.

One bright spot resulting from the talks, city officials said, is an optimistic expectation that the FTA will consider the city’s request to extend the deadline for coming up with a recovery plan for the project funding beyond the current Dec. 31 deadline.

The Honolulu delegation that traveled to the FTA’s western regional office included Caldwell, Martin, Council Transportation Chairman Joey Manahan, Honolulu Authority for Rail Transportation Chairwoman Colleen Hanabusa and HART acting Executive Director Michael Formby.

Leading discussions on the FTA side was Acting Administrator Carolyn Flowers.

Caldwell told the Honolulu Star-Advertiser on Tuesday night, “They said no to any additional dollars under the New Starts program.” He added that the city was told all the money for that program has been committed to other projects.

Martin, in a news release, said the city delegation was told there are 60 other transit-related projects being funded through the program.

Caldwell said this was his third time asking for additional federal transit dollars. “That doesn’t mean I won’t do it again,” he said, adding that the November election and a new presidential administration could bring new opportunities.

“With the end of this cycle, with the new year starting, with a new administration in place and maybe a different makeup in Congress, and a new budget cycle, there’s a possibility, and that’s why I would ask again,” Caldwell said.

In a surprising change in position, Martin said Tuesday he intends to join Caldwell at the Legislature in seeking an extension of the surcharge, especially because the FTA made it clear that pausing the project at Middle Street would be unacceptable and jeopardize the $1.55 billion federal share.

“I’ve been opposed to going back to the Legislature to ask for a further extension of the GET surcharge, but given the FTA’s position, it is clear that we don’t have a choice,” Martin said in a separate statement. “This project is too often viewed as a city issue but it’s a quality of life issue for the people of Oahu who are struggling with some of the worst traffic congestion in the country.”

[8/31/16] http://khon2.com/2016/08/30/fta-on-rail-route-downtown-minimum-ala-moana-ideal/

[8/19/16]  Dan Grabauskas resigns

[8/7/16] Hawaii's is not the only city with rail budget woes

[7/31/16]  Rail’s concrete pathway now snakes more than 8 miles, stretching from East Kapolei almost to Aloha Stadium. Soon, a new construction contract will extend it as far as Middle Street. From there, the rail system’s endpoint, Ala Moana Center, sits 4.3 miles away.

Any solution to keep building toward Ala Moana Center — should city leaders opt to pursue that route — would likely involve a patchwork of funding sources.

[7/8/16] In the latest whistleblower lawsuit to be filed in relation to Honolulu’s rail project, a former Kiewit Infrastructure West Co. manager alleges the firm failed for years to adequately follow environmental laws while building the line’s first 10 miles to Aloha Stadium.

The suit claims that local Kiewit supervisors repeatedly dismissed and downplayed his efforts to keep the firm compliant and that Kiewit violated Hawaii’s Whistleblower’s Protection Act in eventually letting him go. It seeks unspecified compensation for damages.

[6/17/16] Caldwell recommends stopping rail at Middle Street

[4/22/16] As the Honolulu rail agency’s new board chairwoman, former U.S. Rep. Colleen Hanabusa must now help guide the largest public works project in state history as it faces growing financial uncertainty and eroding public confidence.

Hanabusa’s fellow Honolulu Authority for Rapid Transportation volunteer board members unanimously voted to appoint her to the top post Thursday, the day after Mayor Kirk Caldwell reappointed her to a new term that will last through 2021.

“This decision did not come easily. However, I believe the board is at an important juncture,” Hanabusa said moments after becoming chairwoman. “I am doing it because I feel the board has to be very accountable to the public. I feel that we can work together and do the public’s bidding.”

Their vote came during a spirited, daylong meeting in which board members said that HART employees give them “fuzzy numbers” instead of the budget details they need to provide oversight, called for reforms to give them more authority and met in closed session to evaluate the performance of HART’s embattled executive director, Dan Grabauskas.

Hanabusa will serve the rest of former board Chairman Don Horner’s term, which expires this summer, plus a year after that. Vice Chairman Damien Kim briefly served as interim chairman prior to the vote for Hanabusa. Kim, who serves as business manager and financial secretary for the International Brotherhood of Electrical Workers Local 1186, is expected to be appointed chairman after Hanabusa.

[4/12/16]  Don Horner, who once oversaw the state’s largest financial institution, will no longer help oversee the state’s largest public works project.

Horner tendered his resignation to Mayor Kirk Caldwell on Monday as the rail agency’s volunteer board chairman, as the transit project faces rising costs and growing uncertainty.

Horner’s move follows several weeks of upheaval for rail management, in which the city’s top elected leaders have repeatedly put in writing their crumbling faith in the Honolulu Authority for Rapid Transportation’s handling of the project, now estimated to cost nearly $7 billion. HART leaders say the skyrocketing costs are mainly due to construction market forces beyond their control.

Horner delivered his resignation letter to Honolulu Hale five days after Council Chairman Ernie Martin called on Horner and HART Executive Director Dan Grabauskas to resign, and several days before a critical report from the city auditor’s office will be released. In a news conference Monday, Caldwell said that he had already planned to ask for Horner’s resignation prior to Martin’s request. Caldwell was out of state on vacation last week and had scheduled to meet Horner upon his return.

“I just want to make absolutely certain that there’s confidence in this project. And I’ve see an erosion of confidence in this project, both by my administration, by the City Council … and by the public at large,” Caldwell said Monday.

In his resignation letter, Horner said “too often in politics, the focus becomes shooting the messenger of unpleasant news rather than collaboratively working on solutions.” In a separate letter responding to Martin’s concerns, Horner praised HART staff and said Martin’s concerns were a surprise “since we had met a few days earlier, and your concern was not discussed.”

Horner retired as CEO of First Hawaiian Bank in late 2011, after being affiliated with the institution for more than three decades. He also served as the bank’s chairman and president.

Martin is Caldwell’s top political rival and considering a mayoral run against him later this year. Caldwell’s predecessor, former mayor Peter Carlisle, appointed Horner to the HART board for the agency’s 2011 inception. Caldwell said earlier this year that his own reputation is on the line with rail.

Monday, January 04, 2021

2020: A Year To Forget

From the chaos of the global coronavirus pandemic to the continued troubles of the planned rail line, here are the top stories of 2020.

On March 5, Gov. David Ige declared a state of emergency for Hawaii after the death of a passenger from California on a cruise ship that visited the islands. The next day, Ige announced the state’s first confirmed COVID-19 case: a Hawaii resident who traveled on the Grand Princess cruise ship in February.

Hawaii was the first state in the nation to order returning residents and visitors to undergo a 14-day quarantine, dealing a crushing blow to Hawaii’s tourism industry. On March 25, Ige ordered nonessential workers statewide to stay and work at home, further stifling the economy and causing businesses to close and lay off workers.

Due to its dependence on tourism, Hawaii experienced some of the highest unemployment rates in the nation at over 20% at various points of the pandemic.

Caught off guard, health officials scrambled to assess the extent to which the coronavirus was spreading in the community, while struggling with a shortage of test kits, personal protective equipment and other supplies. It took months before the Department of Health established adequate testing and contact- tracing programs. By then, the virus had spread on Oahu, peaking during the summer at more than 300 new cases per day.

In addition to travel and stay-at-home restrictions, the counties placed controls on virtually all aspects of everyday life and commerce, mandating mask wearing and social distancing, limiting gatherings and business operations, and curtailing outdoor activities.

Private and public schools and University of Hawaii campuses switched to online-only instruction in March, optimistic in being able to resume in-person classes by April. For most campuses, it wasn’t to be. Distance learning was still in place when the Department of Education opened the new school year Aug. 17.

On Aug. 27, a second stay-at-home order took effect in Honolulu and was “highly effective at reducing the number of positive COVID-19 cases in the city.” By the fall months, the virus had reached Hawaii’s most vulnerable populations: nursing home residents and those in rural communities such as Kalaupapa on Molokai and on Lanai, while also infiltrating Hawaii prisons and other group settings.

As cases rose, criticism of the Health Department centered on the leadership of Health Director Bruce Anderson and Dr. Sarah Park, the state epidemiologist blamed for failing to build a robust COVID-19 testing and contact-tracing program. Park was placed on paid leave Sept. 4, just four days after Anderson announced he would retire.

A sign of hope came in December, when Hawaii received its first shipment of Pfizer’s COVID-19 vaccine and immunizations of health care workers and first responders began, with long-term-care residents and staff next on the priority list.

As of Wednesday, the Department of Health had confirmed 21,209 COVID-19 cases statewide since the start of the outbreak and a death toll of 285.

***

A TALE OF RAIL

A year ago this week, officials with the then-$9.2 billion Honolulu rail project said confidently that they expected the first leg of rail to be open by the end of 2020.

A year later, with the East Kapolei-to-Ala Moana line still not operational, rail officials are again hoping operations can get underway — sometime after the midway point of the new year.

The past 12 months have been among the most tumultuous chapters in the bittersweet tale of the now $11 billion-plus (including financing costs) project. On the one hand, the rail is facing more questions about its financing than ever before. On the other hand, all signs point to the project’s first leg — from East Kapolei to Aloha Stadium — finally being on track to open in 2021.

And the year appears to have ended on a good note: On Monday, the Federal Transit Administration formally announced the city will have an additional year to come up with a satisfactory financing plan that will allow $250 million in promised funding to finally be delivered.

Also Monday, HART Board Chairman Tobias Martyn announced the agency had selected longtime city Environmental Services Director Lori Kahikina as its interim director, replacing much- maligned Executive Director and CEO Andrew Robbins, whose $317,000-a-year contract was not renewed.

Robbins, first appointed in 2017, has had a rocky relationship with a majority of the board, Mayor Kirk Caldwell and Honolulu City Council leaders. Among the key points of contention was his role in HART’s pursuit of a public-private partnership to build the final 4.1-mile, Middle Street-to-Ala Moana segment, as well as a major transit center at Pearl Highlands, and then operate the line for the first 30 years.

In September, the Caldwell administration announced it was withdrawing its support from the public-private partnership process and urged Robbins and the HART board to switch gears and proceed with a more traditional design- build delivery model. Despite pressure from an increasingly vocal majority on the board, Robbins wanted to stay the course.

Details of the two private partner proposals that had been submitted were finally released at the beginning of December and both were found to be more than $1 billion higher than the $1.4 billion HART officials had anticipated.

Meanwhile, HART and city leaders are facing the financial uncertainty of the ongoing COVID-19 pandemic, since the bulk of rail funding relies on state general excise and hotel room taxes. Caldwell in mid-November said his experts are telling him the project will now cost $11 billion, with financing, and that it could be as late as 2033 before the last Ala Moana station is completed. Officials acknowledge the remainder of the rail project likely will have to be built in segments as funding permits.

Friday, June 17, 2016

Caldwell recommends stopping rail at Middle Street

With rail facing a more than $1 billion budget hole, Honolulu’s top elected leaders now aim to stop construction four miles and eight stations short of what was planned, leaving crews to build the most challenging, expensive and critical stretch at some future date, if possible.

“I wish we could go all the way to Ala Moana now. That’s for another day,” Mayor Kirk Caldwell told rail board members during their meeting Thursday, officially abandoning hope of finishing the entire rail project with its current funding, and instead urging the board to recommend a shorter rail line for now.

“I think we need to focus for now on how we get to Middle Street,” Caldwell said.

Critics of that plan say it undermines the point of building the rail in the first place: to offer West and Central Oahu commuters a more convenient way to get to town. It would significantly reduce ridership from the city’s longtime estimate of 119,000 daily rail trips and place a bigger burden on taxpayers to subsidize the line in place of lost fare revenues, they say.

Eliminating the eight stations past Middle Street could reduce rail’s ridership by at least 51,000 daily boardings, according to Honolulu Authority for Rapid Transportation estimates. The move might solve some of the rail’s immediate money problems, but it could also leave city officials with more difficult long-term challenges as they try to pay for its operations, one key state lawmaker said.

Nonetheless, faced with new cost estimates that put Ala Moana Center well out of reach — and an Aug. 7 deadline from rail’s federal partners to come up with a realistic plan that’s on budget — Caldwell and City Council Chairman Ernie Martin this week endorsed stopping at Middle Street for now.

“It is clear that the benefits of such a plan outweigh the drawbacks,” Martin wrote in a letter Tuesday to Federal Transit Administration Regional Administrator Leslie Rogers. “It does not preclude us from eventually completing the full 20 miles and 21 stations” when the city has the financial means to finish it.

HART officials have estimated it would cost about $6.22 billion to complete the first 16 miles and 13 stations to Middle Street. Rail can expect to receive construction revenues of approximately $6.8 billion, based on the latest estimates. However, it’s now expected to cost more than $8 billion to build the full 20 miles.

“It’s not a perfect-world situation,” HART board Chairwoman Colleen Hana­busa said at the Thursday meeting. “But … we don’t have the money.” The board could schedule a special meeting as early as next week to make a recommendation to the City Council on the Middle Street idea, she said. The Council would then have to discuss what rail policy it wants to pursue during its own meeting, she added.

Even if the city opts by Aug. 7 to pursue the Middle Street plan, there’s no guarantee that the FTA will approve the idea and agree to provide the project’s full $1.55 billion in federal funding. HART officials say FTA leaders have told them the system needs to be “functional” but that there aren’t specific guidelines for what that means.

Earlier this week Caldwell had still been pushing to get the full 20-mile line built.

“I believe we should work to the goal of building the full 20 miles, 21 stations. But we shouldn’t cap. We shouldn’t cut and run,” Caldwell said during an interview on Hawaii News Now’s “Sunrise” morning show several days ago. “This project is just too darn important. It’s something we’ve been fighting for 40 years here.”

The news that both Caldwell and Martin agreed work should stop at Middle Street surprised some members of the City Council’s Transportation Committee, which also met Thursday. Kymberly Pine, who represents the Leeward Coast, was deeply frustrated.

“That’s pretty stupid,” Pine told HART staff after they briefed her. “As someone who’s stuck in traffic the longest … I can tell you, you need to look at the ridership numbers on all these plans.” HART officials say they’ve just begun to analyze how stopping at Middle Street would affect ridership and other factors.

***

A month ago, even with an $8.1 billion price tag on rail, Mayor Caldwell vowed to build rail to Ala Moana. Why did he flip flop and now agrees with Charles Djou to stop rail at Middle Street? Because his and other polls reveal he is trailing Charles Djou badly, said Ben Cayetano, the former governor and unsuccessful candidate for mayor in 2012.

-- Richard Borreca, June 19, 2016

***

Caldwell hedged his position on Friday, asserting that continuity of the project would not necessarily be broken. The mayor pledges to secure other funding to complete the full alignment as designed, proposing to seek it from federal, state and private sources. But there’s no indication that this money will materialize in time to keep construction on track, or ever.

The only thing that is clear is that, as described, the project will end at a point where it’s projected to lose about half its ridership. Commuters won’t flock to ride the rail if, at Middle Street, they’ll have to disembark and wait for a bus to their urban-core destination.

That result wouldn’t justify the investment Honolulu’s taxpayers already have made.

Then, once the forward drive to complete the project is allowed to stall out, inertia would settle in. When the project is finally completed — if it ever restarts — the full pricetag would be higher than it would be if the city stuck to the current plan. That much is certain.

***

A million years from now

Monday, March 28, 2016

rail to open with 10 mile route

Local rail officials have decided that for the opening of the transit system, they won’t extend the route to Middle Street after all.

Instead, they’ve opted to stick with their planned, shorter opening route to Aloha Stadium — a distance of 10 miles. Last summer the Honolulu Authority for Rapid Transportation announced it would revisit the logic of that opening route and the “limited ridership” it would attract.

But as project delays have piled up, the idea of waiting to start service until Middle Street comes online has become less practical. Opening to Aloha Stadium remains the better option, HART Executive Director Dan Grabauskas said last week.

The opening should now occur sometime in late 2018, HART projects.

Service along the entire 20-mile line, from East Kapolei to Ala Moana Center, should now start in 2022, the rail agency estimates. The project is about two years behind schedule following lengthy delays from legal challenges, premature construction starts and other holdups.

Friday, October 16, 2015

rail costing more than expected (surprise!)

[10/16/15] The cost of the city’s rail project is now expected to swell to $6.57 billion as rail officials Thursday made public a new outline of the rail financial plan that incorporates additional utility work, traffic signals and finance charges that had not been included in previous cost estimates.

Honolulu Authority for Rapid Transportation officials also announced the projected opening date for the entire length of the 20-mile project will likely slip again, with the latest projections showing the entire project is now expected to open to the public in the last quarter of 2021.

The official rail financial plan the city submitted to the Federal Transit Administration in 2012 projected that the rail project would cost $5.26 billion and that the entire 20-mile driverless train system would open by mid-2020.

The new projections are part of a financial and scheduling update for rail that is required by the FTA, and mark the third time in a year that rail project planners have publicly amended their calculations to account for delays or project cost increases.

[5/25/15] Officials have increased their estimates for how much it will cost to operate Oahu's rail transit system once it's up and running.

Previously, in a 2012 report, they had projected an annual cost of $116.7 million to operate the rail line in 2021, about a year after the rail system fully opens.

Now, documents provided to the state's finance director revise that figure upward. In a draft report, the Honolulu Authority for Rapid Transportation anticipates it will cost $130 million to run rail in 2021.

Anticipated higher electricity costs — and more consumption of that energy by the rail system — are partially to blame for the estimated $13 million increase for 2021, HART officials say. Inflationary costs are steeper than what had been estimated for the project's 2012 financial plan, they add.

HART leaders emphasize that the latest revisions are preliminary figures, and that they released them in draft form to help state lawmakers weigh whether to extend Oahu's rail tax during their most recent legislative session.

"We're constantly checking numbers and trying to revise them," HART Executive Director Dan Grabauskas said recently. "We were asked to give the most current information we have even though it isn't final. Some of this stuff is still just a work in progress."

HART is expected to release later this year a new financial plan for the project, including its official updated cost estimates.

The Legislature did eventually pass a five-year extension of the rail tax. The measure looks to raise an additional $1.8 billion to finish construction of the 20-mile system, and would explicitly prohibit using those dollars for future system operations.

It's not clear yet whether Gov. David Ige will sign the five-year tax extension into law.

Meanwhile, as the cost estimates increase, it remains unclear exactly how those rail operations and maintenance costs will be covered. Transit leaders have said it could be another two years or so before a detailed plan emerges.

They've said that they need to set the rail system's fares first, and then they'll know how many dollars will be needed on top of that to cover the full operational costs.

The updated operations cost figures, provided to Ige administration Finance Director Wes Machida, estimate that the system will take in $35 million in revenue in 2021, leaving the city to cover the additional $95 million or so in operations costs for that year.

[12/19/14] Facing lagging revenues and soaring costs, Oahu's rail transit system — the largest public works project ever built in Hawaii — finds itself at yet another crossroads.

The 20-mile, 21-station project is now on course to cost anywhere between $550 million and $700 million more than originally thought, rail officials revealed in their latest "project risks update" report Thursday during a Honolulu Authority for Rapid Transportation board meeting.

They blamed the price hike on as much as $190 million in added costs from construction delays, combined with the prospect of soliciting bids for the project's remaining contracts in a booming construction market.

Meanwhile, the project is $41 million behind what officials had expected to collect so far in Oahu tax surcharge revenues. Those general excise tax dollars are supposed to fund about two-thirds of the project.

[12/31/14] Mufi's take

Wednesday, April 01, 2015

not zippy

State Department of Transportation officials hope that Wednesday morning's commute will go smoothly — with the H-1 ZipperLane still open for town-bound traffic — but there's no guarantee that pau hana drivers won't see a repeat of Tuesday's carmageddon that caused widespread gridlock.

The fix depends on whether a mainland technician expected to arrive at 11 a.m. Wednesday will be able to get either of the state's two ZipMobiles running again to return the ZipperLane to its normal operation in time for the afternoon commute.

On Tuesday the ZipperLane remained stuck, cutting off two of the H-1's four lanes from the airport viaduct at Sand Island to the Wai­awa overpass, where the H-1 expands to six lanes.

By midafternoon it took drivers more than 40 minutes to travel 5 miles from downtown to Hono­lulu Airport, DOT officials said.

And it took more than three hours to get from downtown to Mili­lani and to Kapo­lei. Westbound H-1 traffic backed up as far as Wai­alae Avenue in Kai­muki.

The technician from the ZipMobile vendor, Zip U There, was slated to arrive from the mainland with fresh battery packs to replace the ones that inexplicably failed Tuesday.

Ed Sniffen, deputy director of the DOT's Highways Division, said he hoped the technician can solve the underlying problem that caused the battery packs to fail in the first place — and get the ZipMobile running to put the ZipperLane back in time for Wednesday's pau hana traffic.

The snag did not mark the first-ever ZipperLane problem.

On Jan. 17, 2014, one ZipMobile shut down the eastbound ZipperLane for the morning commute when its brakes locked up, and an axle had to be removed from the backup machine to return the first ZipMobile to its barn.

Tuesday's daylong traffic troubles began while the ZipMobile was closing the town-bound ZipperLane at 8:30 a.m. in the Wai­kele area.

Then at 9:30 a.m. "the ZipMobile died," Sniffen said.

ZipperLanes normally increase the H-1's capacity by an additional 2,200 vehicles — or 25 percent — every hour during the morning commute, Sniffen said. An estimated 4,600 vehicles use the H-1 ZipperLane every weekday, he said.

After the ZipMobile died Tuesday, technicians swapped out a battery pack from the state's other ZipMobile, but the replacement battery pack also failed.

"So the computer can't run the ZipMobile," Sniffen said.

By the time the disabled ZipMobile was towed away at 3 p.m., traffic was already terrible.

Then it got worse when a traffic accident in front of Kahana Bay closed lanes in both directions on Kame­ha­meha Highway for roughly one hour, starting at about 4 p.m.

"We absolutely apologize to the public," Sniffen said.

DOT's two ZipMobiles are 17 years old, and officials are working with Zip U There to figure out how much it would cost to overhaul them, Sniffen said.

The life span of a ZipMobile is estimated to be 20 years, Sniffen said.

***

Honolulu is number three!

Tuesday, March 31, 2015

citizens sound off about rail

Mayor Kirk Caldwell, along with state lawmakers who soon will decide whether to approve a rail tax extension, faced a chorus of angst and frustration from residents Monday over the direction of Oahu's transit project.

At a heated town hall meeting at Washington Middle School, a mix of mostly rail opponents and community members concerned about the project's skyrocketing costs sounded off to the political leaders.

Some speakers expressed concern that extending Oahu's 0.5 percent general excise tax surcharge past 2022 would burden a community that's already challenged to make ends meet. Others questioned whether the project is being properly managed — and whether the island could afford it.

"I plead with you, the state lawmakers … I don't want this tax extension. We already have the highest taxes in the nation," Joey Brown, an 18-year-old student at the University of Hawaii at Manoa, implored the panel of county and state lawmakers.

Caldwell told the crowd of 100 or so people that the rail transit system remains critical for an island that's already overrun with cars and only getting more crowded — despite the project's ballooning cost overruns and a budget gap of as much as $910 million.

"I do not want to build another freeway on this island, or another major road," Caldwell told the audience Monday. "I want to make better use of the lands that are zoned urban."

Caldwell and rail leaders have insisted that rail will need a tax extension in this legislative session to overcome the project's fiscal woes and keep construction on schedule. Legislators are weighing two bills that would grant an extension.

Gov. David Ige, meanwhile, has consistently expressed skepticism about the need to extend the tax during this session.

A group of McCully- and Moiliili-area lawmakers, including state Reps. Scott Saiki (D, Downtown-Kaka­ako-McCully), Della Au Belatti (D, Moiliili-Makiki-Tantalus) and Scott Nishi­moto (D, McCully-Moiliili- Kapa­hulu), along with state Sen. Les Ihara (Moiliili-Kai­muki-Palolo) and Hono­lulu City Councilwoman Ann Koba­ya­shi, put together the forum with Caldwell and rail officials.


The organizers were overwhelmed by about 50 written questions in addition to the constant line of residents waiting to take the microphone.

Thursday, December 04, 2014

the first mile

City and rail officials eagerly showed off the transit system's first 220 feet of track on Wednesday and gave the first public view from atop the so-called elevated guideway 37 feet above farmland in East Kapolei.

"We're really seeing the project become reality," said Councilman Joey Manahan. "Today's the first of many milestones for the project."

After delays caused by a lawsuit and the failure to gain all necessary permits before construction began on the West Oahu/Farrington Highway segment, Dan Grabauskas, executive director and CEO of the Honolulu Authority for Rapid Transportation, said Wednesday that the first elevated guideway was slightly ahead of schedule.

Construction crews were supposed to have the first mile of elevated guideway ready by Wednesday for what will be the Ho‘opili Station, the third of 21 stations planned for the $5.26 billion project.

Instead, workers finished building a 1.25-mile stretch by Tuesday.

The track is laid down on the horizontal concrete guideway.

Mayor Kirk Caldwell got stuck in traffic driving from Honolulu Hale to Kapolei and said the 42-minute commute by rail from the start of the system at the Kroc Center Hawaii to Ala Moana Center will improve life for commuters.

Despite a misty, gray view from the top of the rain-soaked guideway Wednesday, Caldwell said people will be impressed when they finally see it close up.

"It's actually pretty darn nice," Caldwell said. "Most people will be pleased at how it looks. Visually, it's much narrower than the H-1 viaduct and the elevated freeway in Kahala."

Friday, August 15, 2014

rail transit bids exceeding budget

New construction bids show the costs to build Honolulu's rail transit system are rising sharply -- and local transit leaders remain uncertain whether they'll ultimately be able to deliver the project on budget.

This week, rail officials opened three bids to build the transit system's first nine stations. Each of those bids exceeded the project's budget for that work by more than $100 million.

The least expensive bid -- a $294.5 million proposal from Nan Inc. -- still exceeded what rail officials had budgeted by about 60 percent.

"Clearly our estimates right now are suspect," Honolulu Authority for Rapid Transportation board Vice Chairman Don Horner said Thursday.

[surprise surprise surprise]

Sunday, June 22, 2014

still talking about rail

Karl Kim's list of top ten fixes
Kirk Caldwell writes to residents of Honolulu in 2039
Dan Grabauskas: you can judge us in 25 years
Ben Cayetano: the future doesn't look bright

see also Oahu Rail Transit?

Friday, November 16, 2012

Oahu rail transit?

[11/16/12] Cliff Slater isn't giving up

[10/5/12] Mayoral contenders Kirk Caldwell and Ben Caye­tano continued to poke holes in each other's mass transit plans during a final forum on live television Thursday night.

A majority of the hourlong "Insights on PBS Hawaii" program on KHET was devoted to the city's $5.26 billion rail project, which Caldwell supports, and Caye­tano's alternate $1.5 billion Flexible Affordable Smart Transportation plan.

Cayetano was put on the defensive first, with Caldwell questioning its actual cost and funding sources.
Tunnels through the Kapiolani corridor that are part of the FAST plan will cost more than anticipated, Caldwell said, because "you will basically have to trench or tunnel for long distances right through the heart of our city."

Further, he said, "there's no financing for this project."

Cayetano said Caldwell's questioning of the tunnel segments "shows his ignorance" of the FAST plan.
"The tunnels are short," he said. "They're basically underpasses."

As for his plan's Nim­itz flyover, Caye­tano said that Gov. Neil Abercrombie told him just before the forum that "he's game" for a partnership with the city.

[10/4/12] Former Gov. Ben Cayetano's campaign team revised the cost of the transit plan he unveiled last week, increasing the projected cost to $1.5 billion from $1.2 billion.

The cost of construction has not been revised, said Cayetano staffer Sam Callejo. Instead, the total price tag was increased to include a 20 percent contingency plus finance charges, making the plan a more “apples and apples” comparison with the city’s $5.26 billion rail transit plan.

[9/30/12] Star-Advertiser editiorial / Cayetano on FAST / Caldwell on FAST

[9/27/12] Former Gov. Ben Cayetano unveiled a transportation plan today that features new Bus Rapid Transit routes, high-tech traffic signal systems to instantly respond to traffic snarls and plans for two-lane underpasses to ease the flow of traffic on Kapiolani Boulevard and other thoroughfares.

The Cayetano plan would also feature a two-lane extension of the double-decked segment of Nimitz Highway, and would route express buses along a newly created dedicated bus shoulder lane on the Moanalua Freeway.

Cayetano estimates his plan, dubbed the Flexible Affordable Smart Transportation or FAST, would cost $1.1 billion, or about one-fifth the cost of the Honolulu rail transit project.

Cayetano is running for mayor, and promises to halt the city’s $5.26 billion rail transit project if elected.

[8/27/12] The city has agreed to temporarily halt all construction on the $5.26 billion rail project apart from some short-term tasks required for an orderly shutdown, the Native Hawaiian Legal Corp. said today.

NHLC lawyer David Kimo Frankel met with city and rail officials Monday afternoon, and issued a statement that “It is our understanding that the City has halted construction of the rail project.”

“For all intents and purposes, construction of the project has been halted although there may be some narrowly tailored, low-impact exceptions,” Frankel said in a written statement. 

Frankel said the city plans to complete “a few short-term tasks for public safety” such as backfilling open trenches, and plans to continue longer-term maintenance activities such as erosion control measures.
The city also plans to complete the required archaeological inventory survey for the 20-mile rail line, and undertake other “miscellaneous activities,” Frankel said in his statement.

He said the city is drafting a list to specifically describe those activities, and will discuss the list with Native Hawaiian Legal Corp lawyers to determine whether those activities should be allowed to proceed, Frankel said.

The NHLC sued the city and state over the rail project, and the Hawaii Supreme Court ruled Friday that the State Historic Preservation Division violated its own rules by allowing the project to proceed before an archaeological survey was completed for the entire rail route.

In a unanimous ruling, the court found that rules governing the SHPD do not allow the SHPD to agree to the rail project until the city finishes the survey to determine if there are Native Hawaiian burials or other archaeological resources in the path of the rail line.

[5/3/12] The three candidates vying for Honolulu mayor engaged in the first debate of the campaign season Wednesday night, touching on a variety of subjects but ultimately trying to score points against one another on the singularly contentious issue of rail transit.

Both Mayor Peter Carlisle and former city Managing Director Kirk Caldwell support completion of the $5.27 billion project, while former Gov. Ben Cayetano has vowed to kill it. Construction began last week.

[3/28/12] Rhetoric is heating up over the financial impact of the city's planned $5.27 billion rail transit project as two top contenders for the mayor's job traded accusations Tuesday of reckless spending and misinformation.

Former Gov. Ben Caye­tano said the city's prioritization of rail has taken as much as $17 million away from core city services such as public safety, flood control, road paving and street lighting.

"I have contended throughout the course of this campaign that the city's policy of spending without doing due diligence is leading this city to a financial disaster of epic proportions," Caye­tano said at a news conference Tuesday.

Mayor Peter Carlisle accused Caye­tano of trying to create "fear and confusion" about the cost of the rail project by misrepresenting budget presentations made by his administration.

"This is tired old politics as usual," Carlisle said. "From the very beginning, my commitment has been to spend our money wisely, no matter what the spending is for.

[2/23/12] Mayor Peter Carlisle delivered his second state of the city address today, highlighting some of his administration's achievements and outlining his vision for the future of Honolulu.

He repeated his commitment to the city's $5.27 billion rail transit project, calling it the only option for sustaining a city that is expected to top one million in population in the next decade.

"This is the only viable option for building this 21st century and providing a sustainable future for all of Oahu that has made it through decades of vetting and is poised to employ people now," Carlisle said in prepared remarks.

Carlisle also pledged greater transparency by the city as the project moves forward.

"It starts with leadership and expecting the (Honolulu Authority for Rapid Transportation) board to provide the necessary oversight to satisfy the public," Carlisle said. "It means setting clear rules regarding change orders, delays, shoddy workmanship and oversight."

Carlisle has said he and his administration will be providing more facts on the rail project to combat negative information being spread by rail opponents. A recent poll indicated that public support for the rail project has declined, with more people against the completion of the project.

"I recognize many residents question the city's ability to answer questions transparently, to address issues that have been raised, and to deliver the project on time and under budget," he said. "Given its price tag, you have a right to scrutinize it and to feel concerned. I feel those concerns, as well."

[11/16/11] Keith Haugen responds to Bob Jones

[11/2/11] Bob Jones on rail: ugly, expensive, but necessary

[9/21/11] Although retired now, Cayetano has plenty of insightful opinions regarding Hawaii politics and the decisions being made for our communities, including his opposition to the rail system.

“Other than my family, it’s the only thing I’m really involved in these days,” he says.

“As chairman of the (state Senate) transportation committee, I was opposed to it even then, and that carried over to my lieutenant governorship and finally my governorship and now. As I look further, I believe it would be financial disaster as the construction costs are being estimated low and the ridership is unrealistically high, and that seems to be a pattern with most rail projects,” says Cayetano, who was featured on MidWeek‘s cover Oct. 30, 1996.

“There are many alternatives that the city hasn’t looked at,” he adds. “One of the big issues is the city failed to include other alternatives in the Alternative Analysis Report, which is required, which is supposed to be provided by these policy makers.”

Cayetano favors the idea of a bus rapid transit system that, to him, would “do substantially everything that light rail would do, but at substantially less cost.”

[8/21/11] Walter Heen, Ben Cayetano, Cliff Slater, Randall Roth are challenging the processs by which the city chose elevated heavy rail.

The city has paid more than $2 million in taxpayer money to 10 different public relations firms to promote its heavy-rail project. Here's what they have not yet told you

[2/12/11] Make that February

[1/19/11] Rail project to break ground in March

[10/26/09] Is modern Oahu like ancient Greece? Full of tyrants and myths? At least when it comes to rail, yes. Only a tyrant would tax people for a rail project years before the proposal has been found to be environmentally acceptable and federally funded. Only a tyrant would award contracts unlawfully for a project that has neither state nor federal environmental and other approvals. Only a tyrant would manipulate the process in order to ignore superior and lower-cost alternatives such as bus rapid transit and true light rail. -- Panos D. Prevedouros

[10/13/09] Even when I disagree with former Gov. Ben Cayetano's positions, such as his anti-rail stance, I have always respected his honesty. In that spirit, I would like to correct the misinformation in his Oct. 9 Star-Bulletin interview about the Honolulu rail transit project. ... the ridership projections utilize forecasting models that have been approved by the FTA. Our partners in the federal government would not have allowed the project to advance this far if our facts and figures did not meet their stringent standards. -- Kirk Caldwell
Managing director, Honolulu City & County

[10/9/09] Ben Cayetano on transit: First of all, the mayor's rail transit plan is so expensive. They estimate $5.6 billion, something like that. If the historical patterns on the mainland follow through, you can probably add another $2 billion or maybe even $3 billion to that. And they're forecasting unreasonably high ridership. That means that real property taxes are going to go up, and the cost of living is going to go up. And I don't think it's going to relieve traffic congestion to the point that it's worth the cost.

[10/1/09] Rail still being debated
Oahu will benefit from rail, but make sure it's elevated
All-elevated rail will be costly, inflexible and ugly

[8/19/09] The sad truth is that the city has been promoting the Vancouver overhead rail, which was built many years ago for a city twice the size of Honolulu. Since then, many cities much larger than Honolulu have determined that overhead rail is just too expensive, and that light rail at grade or managed traffic lanes are a better alternative. The city, however, continues on its Web site to erroneously misinform the taxpayer by promoting the Charlotte and Phoenix rail projects, which are light rail at grade and are nothing comparable to the Honolulu project. -- Geoffrey Paterson, AIA Emeritus

[6/24/09] An executive with one of the largest architecture and planning firms worldwide said rail projects such as the one planned on Oahu will help increase business along the transit line. "It's not just about moving people around. ... I think it's a catalyst for change," said Ian Mulcahey, a lead planner for the London-based firm Gensler. "It will enable the city to grow."

[6/20/09] A former government official in Canada who helped to build the Vancouver SkyTrain said he thinks Honolulu is making the right decision in developing an elevated rail system. Dan Doyle, former deputy minister of British Columbia's Ministry of Transportation, said the SkyTrain has significantly increased efficiency, reduced the need for motor vehicles, and enabled the city to host the 2010 Winter Olympics. "Without those rail lines, we would not be able to do it," said Doyle, now executive vice president of the 2010 Winter Olympics.

[6/9/09 writes Panos Prevedouros] Honolulu's City Council, which represents almost 900,000 people on Oahu, is about to make a major fiscal and political error. It is about to grant the authority to the city administration to start rail without environmental approvals and without federal monies. It also plans to approve to start the project about a mile outside Kapolei and develop a six-mile elevated rail to Waipahu.

Worse yet are plans to approve the float of $1.1 billion in bonds for rail with no stipulations or accountability controls. This $1.1 billion obligation must be paid back by the Oahu taxpayer, plus interest.

[4/30/09] Wayne Yoshioka responds to Bainum

[4/27/09] Architects propose street-level rail (writes Duke Bainum)

[10/22/08] This Honolulu Rail Transit Q&A provided by the City and County of Honolulu was turned into a glossy brochure distributed with the Star Bulletin and Midweek (and I assume the Advertiser)

[10/16/08] The Star Bulletin editorializes. A radical change at this point would undoubtedly jeopardize federal funding, especially during the nation's current economic meltdown. Not only is Kobayashi wrong in assuming that revenue from the general excise tax surcharge could be spent on her plan, her hope for $2.4 billion in federal funding to foot nearly the entire bill is preposterous.

[10/15/08] Mayoral candidate Ann Kobayashi unveiled her new mass-transit plan yesterday to build elevated three-lane highways for zipper lanes and buses that she says would be 62.5 percent of the cost of Mayor Mufi Hannemann's proposed rail transit system.

[10/15/08] Dan Boylan writes The construction of a rail transit system will do more than provide a long-term transportation alternative. It also will provide an economic stimulus that could help sustain us in these difficult times.

[10/4/08] Rail will bring jobs and federal dollars

[9/5/08] Car expenses higher than rail?

[9/4/08] Stop Rail Now fails to get proposal on ballot

[8/23/08] Numbers on rail don't makes sense

[8/21/08] City Council approves ballot question on transit

[8/5/08] City Clerk refuses anti-rail petition

[7/28/08] Poll on Hannemann handling rail: 35% above average, 30% below average.

[7/28/08] 40% say they're likely to ride rail

[7/25/08] Hannemann working with City County on charter amendment

[7/24/08] The City Council yesterday voted unanimously to put the issue of whether to build a commuter rail line on the November ballot. The 9-0 vote was the first of three needed to adopt the measure, which could be vetoed by Mayor Mufi Hannemann.

[7/20/08] "We now must let the people of Oahu vote at the ballot box and settle this debate once and for all," writes Charles Djou

[7/17/08] Stop Rail Now consider legal action

[7/16/08] Stop Rail Now petition derailed by City Clerk

[7/15/08] In his latest promotion of the city's proposed $4 billion rail transit system, Mayor Mufi Hannemann called a news conference yesterday at which four former state transportation directors endorsed the project.

[7/12/08] Lingle signs petition

[7/4/08] Hannemann says Lingle waffling on rail

[7/3/08] Lingle likely to sign anti-rail petition

[7/2/08] Rick Hamada's take

[7/2/08] A continuing debate on the Internet between the pro- and anti-rail groups has shaped much of the conversation surrounding the city's planned $4 billion rail transit system.

Panos Prevedouros to run for mayor against Hannemann.

[6/30/08] Rick Tubania says Callan and Uechi are full of it

[6/29/08] Cayetano enters the fray

[6/29/08] No Rail (says Stop Rail Now). Go Rail (says City Department of Transportation Services).

[6/29/08] Jamie Story responds to Hannemann

[6/26/08] Local bank economists and real estate developers openly admit that rail is about property development - not a transportation solution. The Hannemann Committee ad in both dailies on Sunday was a diversionary tactic to deflect public attention away from important facts and issues [says thee Hawaii Highway Users Alliance]

[6/26/08] Mayor Mufi Hannemann criticized the media for doing a poor job of challenging opponents attempting to stop the city's planned $4 billion rail-transit project, prompting him to spend campaign funds to take out advertisements.

In his first interview since ads ran in Honolulu's two daily newspapers last weekend, Hannemann said yesterday he stands by his assertions that the local anti-rail campaign is backed by mainland companies and individuals connected with the oil and automobile industries.

[6/24/08] Mayor Mufi Hannemann has launched a series of ads using his campaign funds against a group attempting to stop his plans to build a $4 billion rail transit system.

[6/18/08] Reader can't figure out Al Chase

[6/15/08] Al Chase can't figure out anti-rail logic

[3/2/08] While managed lanes, HOT lanes or bus lanes can be a useful complement to a fixed guideway system, such approaches are no substitute for a permanent rail-based system as the backbone of a regional transit program.

[11/14/07] Hannemann wants experts to decide on fixed-guideway technology

[10/17/07] Kobayashi responds to Kaku

[10/9/07] Melvin Kaku responds

[9/28/07] Rail critics complain to Federal Transit Authority / editorial / response to editorial

[9/11/07] Jerry Coffee compares transit alternatives [again, guess which one doesn't sound so hot]

[9/2/07] Melvin Kaku counters claims of Dela Cruz and Kobayashi

[8/26/07] Guided bus system is serious option for Honolulu say Donovan Dela Cruz and Ann Kobayashi.

[1/31/07] Mayor Mufi Hannemann wants the city to build a $3.8 billion 20-mile rail line from East Kapolei to Ala Moana Center as its first mass transit segment.

"We have kept in mind that we want to serve a populace area, a major employment center. We also wanted to have this line where we would carry the most future riders and would best meet what the (federal government) calls the cost -effectiveness criterion," Hannemann said yesterday.

The initial line -- called the minimal operable segment -- will begin at the future site of the Ray and Joan Kroc Community Center just above Kapolei Parkway in Ewa and move up the proposed North-South Road to Farrington Highway. Circulator buses will transfer riders from Ewa, Kapolei and other parts of West Oahu to the rail line.

The line will then run through Waipahu, Pearl City and Aiea before passing Pearl Harbor, Hickam Air Force Base and the airport. It will then go through Kalihi, downtown and Kakaako, and end at the shopping center.

"The (minimal operable segment) says what we can afford to do in the short-term so this is what we call 'the first project,'" Hannemann said.

[2/7/07] Michael Lauck responds to Coffee's article

[1/12/07] Jerry Coffee touts the HOT lanes alternative

[12/23/06] The City Council, in a 7-2 vote yesterday, gave final approval to a fixed guideway mass transit system for Oahu but left it to Mayor Mufi Hannemann to decide key segments of the route.

[12/8/06] City Council chooses rail

[12/3/06] Expanded bus system would be better than rail

[11/26/06] Enhanced bus system could be the way to go

[11/21/06] We need to get cars off the roads, not put more on

[10/31/06] Estimated cost for rail transit raised 20 percent (responses)

[10/15/06] Rail or a real solution?

[10/15/06] Mufi is P-R-O R-A-I-L

[10/11/06] more on toll lane capacity

[10/6/06] Councilman Gary Okino responds to David Rolf

[10/1/06] So what's the solution to traffic?

We've now learned that rail will not solve the traffic congestion problem, so voters likely will question any candidate who proposes it as a solution. Particularly since the proposed rail for Honolulu would cost more than $4,000 per person to build -- more than 20 times the cost of other city rail systems. The Dallas rail system cost $204 per person to build.

That's why more and more elected officials and candidates for office in Hawaii are examining the elevated tollway solution proposed by a nonprofit organization known as the Hawaii Highway Users Alliance, [writes David Rolf, executive director of the Hawaii Automobile Dealers Association]

[6/23/06] Councilwoman calls proposed rail transit ugly

[6/21/06] Jerry Coffee on collecting the 0.5% transit tax

[6/6/06] Details of mass transit options are starting to emerge

[5/24/06] Light rail won't reduce traffic says Jerry Coffee

[4/18/06] HOT lanes have been added to the mix of transit alternatives

[1/5/06] It's a done deal says Rick Hamada

[12/10/05] There are two public meetings scheduled and the website is honolulutransit.org (from Mufi's radio commercial)

[12/4/05] City consultants have identified three likely technologies — light rail, monorail and magnetic levitation — and four routes that could be used for a new mass-transit system between Kapolei and the University of Hawai'i-Manoa.

[10/9/05] Start small. Get a high-profile leader, preferably not a politician. Be prepared to stay the course. Those are the things Honolulu needs to do if it hopes to see its latest push for mass transit become a reality, according to transit experts nationwide.

[10/4/05] Hannemann impressed with Sumitomo's rail system

[8/11/05] City Council approves transit tax

[8/9/05] Star Bulletin opinion: new mass transit system is essential

[8/8/05] Transit tax approval not assured

[7/30/05] Hawai'i would get federal authorization for a long-debated Honolulu rail transit system and almost $146 million for roads, bridges and transit systems in a massive $286 billion federal transportation bill approved by the House and Senate yesterday in Washington.

[7/12/05] Lingle won't veto bill after last minute compromise

[7/10/05] The Mayor is not backing down from his viewpoint

[7/7/05] is the title of Susan Page's article in the June 29, 2005 issue of Midweek. There's a lot more on the anti-rail viewpoint at honolulutraffic.com.